About three miles east of Trempealeau, the Great River State Trail used to cross Tank Creek on a 200-foot bridge built in 1957 for the Chicago-Northwestern railroad. On the evening of May 15, 2025, the bridge caught fire. Nobody was hurt, and the Wisconsin DNR called the bridge a total loss. Because of where it sits, there has never been a reroute. Eighteen months later, the DNR's trail notice, updated October 30, 2026, still says the bridge is "closed until further notice."
That changed on paper in October, when the state approved a replacement. Construction will close more of the trail east of the village for a stretch before the gap is fixed. For at least another year, Trempealeau's part of the trail runs northwest, toward Perrot State Park and Marshland.
A $3.8 Million Fix for a 200-Foot Gap
The Wisconsin State Building Commission approved the project at its October 22, 2026 meeting. The request filed with the commission puts the total budget at $3.8 million. Here's how that splits:
| Line item | Amount |
|---|---|
| Construction | $2,660,000 |
| Design | $433,500 |
| Contingency | $399,000 |
| Other fees | $185,100 |
| DFD management | $122,400 |
| Total | $3,800,000 |
The project covers four bridges. Tank Creek is the one people know about. The other three are older bridges on the same corridor, which the state describes as having "severe age and deterioration." The state's filing gives a practical reason to rebuild all four together: Tank Creek is the farthest bridge from the trailhead, and heavy machinery will need sound bridges to get out to it. All four are being designed so they don't raise flood elevations, and Sen. Brad Pfaff told WIZM the new bridges will sit higher and use more durable materials.
The bridge is one of 21 structures on the Great River State Trail, which has more than 3,100 linear feet of bridges in all. The DNR's Tank Creek page says most of them are 100-year-old railroad bridges. Rebuilding three of them now means the stretch east of Trempealeau will come back with newer crossings than the corridor has had in a long time.
The Calendar Runs Through Two More Winters
Here's the schedule, from the fire through the planned finish:
| Date | Milestone |
|---|---|
| May 15, 2025 | Bridge destroyed by fire |
| May 2025 | Design firm selected |
| October 2025 | $364,000 released for preliminary plans |
| October 22, 2026 | Building Commission approves the project |
| March 2027 | Bid opening |
| May 2027 | Construction begins |
| November 2027 | Substantial completion |
| November 2028 | Final completion |
The DNR's own page gives a looser estimate, saying work "may begin in summer 2027." The date to watch is November 2027. Rep. Steve Doyle explained the gap between the two completion dates to WIZM:
"The expectation is we'll have substantial completion in about a year, November of next year, and then final completion a year after. I'm hopeful that substantial completion means that it will be able to be used at that point."
If that holds, the first full season of riding from Trempealeau to Onalaska again would be 2028, about three years after the fire.
Part of the money also depends on decisions in Washington. The state's filing lists a $2,345,000 grant through the U.S. Department of Transportation's Federal Highway Administration. It also notes the project was picked by Wisconsin's Federal Lands Access Program for its 2027–2029 allotment, and that this funding "is contingent upon reauthorization of appropriations from Congress." Of the $3.8 million budget, $3,522,026 is federal money.
Next Summer, More of the East Side Closes
Right now the trail east of Trempealeau dead-ends at the burned span. You can head out from the village trailhead, and from the other direction you can ride from Lytle's Landing toward Midway and Onalaska, but you can't connect the two. Once construction starts, the DNR says "a portion of the trail will be closed between the Trempealeau trailhead and the Lytle's Landing trailhead while work is completed," with signs, barricades and fencing marking the closed area.
So for the 2027 riding season, some of the out-and-back east of the village that's open today will be fenced off. The state's filing describes the trail between Trempealeau and Midway as an approximately 10-mile segment with numerous pedestrian bridges, and that's the stretch where the work will happen.
Local lawmakers pushed for a faster fix. Pfaff told WIZM he had proposed a public-private partnership with the Shovelmen, a Sparta group that has designed and built a number of pedestrian bridges. The state chose a traditional building project instead. "I surely wish that we could have moved this faster," Pfaff said. Doyle called the pace "lightning speed" for a government project. Pfaff also told WXOW that reopening the trail matters to local businesses and tourism.
People in the village said much the same soon after the fire. Trempealeau Hotel owner Amy Werner told the La Crosse Tribune that bike tourists ride into town from the trail, and that local residents use it for recreation too. The same story described River Stop, the village's only gas station, as a pit stop for cyclists and a place to buy trail passes.
The Part of the Trail That Still Runs From the Village
The DNR doesn't list anything northwest of Trempealeau as closed. From the village trailhead, on Trempealeau's east side off WIS 35 with parking and restrooms, it's roughly 8.6 miles to the Marshland trailhead. The route passes Perrot State Park and runs through the Trempealeau National Wildlife Refuge. The DNR's trail map, revised March 27, 2026, labels Marshland as the North Trailhead and lists parking at Perrot and the refuge. Inside the refuge, the straight route is about 2 miles, and an optional loop runs 4.5 miles.
The trail is open year-round. The DNR's recreation rules for winter include:
- Walking, bicycling, cross-country skiing and snowshoeing are allowed, but the trail isn't groomed.
- Snowmobiles are allowed under Wisconsin snowmobile law, so other users share the trail with sleds.
- Each county decides when its snowmobile trails open and close.
- Bicyclists 16 and older need a state trail pass. Skiers don't, and walkers and hikers are exempt.
The 2026 state trail pass costs $25 for the year or $5 for a day. Annual passes expire December 31, 2026, so anyone riding in January will need a new one.
Winter Stops Along the Open Side
Once there's enough snow, the most groomed terrain near the village is at Perrot State Park. The DNR says the park has nine miles of groomed and tracked cross-country ski trails when snow allows, including a one-mile skate-ski section in the campground. Snowshoeing is allowed on trails not groomed for skiing.
The refuge has quieter options. The 1.2-mile Access Marshland trail is open to snowshoeing and skiing, and other seasonal routes stay ungroomed. Dike paths may not be plowed. The refuge contact station is on its fall-winter schedule, open Wednesday through Friday from 8 a.m. to 3:30 p.m. It's closed Saturday through Tuesday and on federal holidays. For Thanksgiving, it closes at noon on Wednesday, November 25, and stays closed through Friday, November 27. It's also closed December 23 through 25, December 31 and January 1. The refuge's Freedom 250 Refuge Relay runs through December 31, 2026. Visit three of its 15 locations to earn a commemorative patch.
For snowmobilers, Trempealeau County's snowmobiling page links to an interactive trail map. Clubs like the Arcadia Sno-Riders are part of the local network, and the county opens trails only after there's enough snow for a safe base.
Back in the village, the Trempealeau Hotel at 11332 Main Street says its hours vary with the weather, so call (608) 534-6898 or check its Facebook page before heading over. River Stop, at 24013 E 3rd St., sells gas, groceries, pizza, sandwiches and breakfast items. Its phone number is (608) 534-7400. To get updates as the Tank Creek project moves through bidding and construction, sign up for the DNR's Great River State Trail email notices.
Trail news like this matters if you're deciding whether to stay in Trempealeau County, downsize or make a move in the next couple of years. Wanda Johnson has worked with Chippewa Valley families for more than 30 years and can help you think through timing alongside the local projects that shape it. Work With Wanda — Schedule a Consultation.